Use the Calculation pane of the Calculations tab in the Resource view to assign a rate set to a result.
To assign a rate set to a result:
-
Display the Resource view for the resource file that you want to update.
-
In the Resources grid of the Resource view, select the resource or child resource containing the result that you want to add a rate set to.
Note: Resources that already have result assignments are denoted by
.
-
Select the Calculations tab.
-
In the Calculation pane of the Calculations tab, select a result.
-
In the Rate Set column, click
to select the rate set that you want to assign to the result. You can only choose from the rate sets contained in the rate file that is assigned to the resource file.
Note: You can change the rate file assigned to the resource file on the General tab of the Resource File Properties dialog box.
-
Click
on the Quick Access Toolbar to save the changes.